1. Purpose

The purpose of this policy is to ensure that all technology and system changes at Bayarcash are managed in a structured and controlled manner. This reduces risks associated with system downtime, data loss, security breaches, or unintended business impact.

2. Scope

This policy applies to:

  • All hardware, software, and network changes within Bayarcash.
  • System upgrades, patches, configuration changes, new application deployments, and integrations.
  • All employees, contractors, and third-party vendors involved in IT systems management.

3. Policy Statement

Bayarcash will:

  • Ensure that all system changes are documented, reviewed, tested, and approved prior to implementation.
  • Maintain accountability and traceability for all changes.
  • Minimize risks to business operations, data integrity, and customer service.
  • Ensure compliance with legal, regulatory, and security requirements.

4. Roles & Responsibilities

4.1 Change Advisory Board (CAB)

  • Reviews and approves all significant changes.
  • Assesses risk, impact, and resource requirements for proposed changes.

4.2 IT / System Administration Team

  • Initiates, tests, and implements approved changes.
  • Maintains change records and documentation.
  • Monitors post-change performance and resolves any issues.

4.3 Employees & Users

  • Report system issues or change-related incidents promptly.
  • Participate in user acceptance testing when required.

5. Change Classification

Changes are classified based on risk and impact:

  • Standard Changes:
    • Pre-approved, low-risk, routine changes (e.g., software patch updates).
  • Normal Changes:
    • Require assessment and CAB approval (e.g., configuration updates, system upgrades).
  • Emergency Changes:
    • Implemented to resolve critical incidents or security threats.
    • Must be documented and reviewed post-implementation.

6. Change Management Process

6.1 Request for Change (RFC)

  • Submit RFCs using Bayarcash’s change management system.
  • Include description, rationale, risk assessment, back-out plan, and schedule.

6.2 Review & Approval

  • CAB evaluates RFCs for risk, impact, and resource requirements.
  • High-risk or complex changes require senior management approval.

6.3 Testing

  • All changes must undergo testing in a non-production environment.
  • User Acceptance Testing (UAT) is required for application or configuration changes affecting business operations.

6.4 Implementation

  • Schedule changes during low-impact windows whenever possible.
  • Implement changes according to approved plans.

6.5 Post-Implementation Review

  • Verify system functionality and stability.
  • Document lessons learned and any deviations from the plan.

7. Documentation & Reporting

  • Maintain a detailed record of all changes, including RFC, approvals, test results, and post-implementation outcomes.
  • Generate regular reports for management review, highlighting trends, failures, and improvements.

8. Risk Management

  • Conduct a risk assessment for every change.
  • Identify dependencies, potential business impacts, and mitigation strategies.
  • Maintain back-out or rollback plans for all non-standard changes.

9. Compliance

  • All changes must comply with:

    • Regulatory requirements relevant to financial operations.
    • Bayarcash internal security and data protection policies.
  • Unauthorized or unapproved changes may result in disciplinary action.

10. Training & Awareness

  • IT staff must receive regular training on change management processes and tools.
  • Users impacted by changes should be informed in advance and trained on new procedures or systems.

11. Policy Review

  • This policy will be reviewed annually or following significant incidents, system upgrades, or organizational changes.
  • Updates must be approved by the CAB and executive management.